b'PELICAN POINTThis project required caissons for the shoring walls down both sides to allow for the construction of the basement and subterranean garage which consisted of a 500+ yard 24 thick concrete mat slab with 12-14 thick concrete retaining walls. At the first floor we poured a 5000 sq. ft. 6 thick pan deck. The project finished out with site walls surrounding the basement for planters and stairs.Year of Completion: 2023Location: Newport Coast, CA24'