b'BAYSIDEPL.This project consisted of a below sea level basement and garage complete with a vehicle turntable. We had to install a dewatering system, shoring piles and lagging in order to excavate the basement before constructing the foundation. The basement floor consisted of a 24 concrete mat slab and substantial concrete retaining walls. The first floor required the installation of a concrete podium deck. The entire project required more than 1,400 yards of concrete.Year of Completion: 2021Location: Corona Del Mar, CA30'